Current City Street and Sewer Projects

 PROJECT COMPLETED

Sanitary Sewer Bond Project

PHASE A

 

Contractor Name:   Texas Pride Utilities

Construction Start Date:  November 7, 2022                           

Substantial Completion Date:  March 7, 2023

Final Completion Date:  March 22, 2023

Project Overview: The project bid package consists of a Base Bid and three Add Alternate Bids.  

Scope of work includes pipe bursting of 1878 LF of lined 6-inch to 8-inch pipe, replacing 63 LF of lined 6-inch sewer pipe by open cut, reconnect 24 sewer laterals, remove, and replace 9 manholes, rehabilitate 10 manholes, install 1 cleanout, abandon 263 LF of lined 6” sanitary sewer pipe, 3-point repairs by open cut, and site restorations.

 SEE PLANS HERE


  PROJECT COMPLETED

Sanitary Sewer Bond Project

PHASE B

 

Contractor Name:   T-Construction

Construction Start Date:  January 9, 2023

Substantial Completion Date:  May 23, 2023

Final Completion Date:  September 7, 2023

Project Overview: The project bid package consists of a Base Bid and three Add Alternate Bids.  Work includes pipe bursting, reconnecting of sewer laterals, installing manholes and one terminal cleanout, performing point repairs, removing protruding tap using a robotic cutter, performing post-TV inspections, restoring landscape and doing appurtenant work.

SEE PLANS HERE


 PROJECT COMPLETED

Street and Drainage Maintenance Project

Contractor Name:   ONO Contracting, Inc.

Construction Start Date:  TBD                               

Substantial Completion Date:  TBD

Final Completion Date:  TBD

Project Overview: The project bid package consists of milling, overlay and installing valley gutters on Park Hill Drive


 PROJECT COMPLETED

Sanitary Sewer Bond Project

PHASE C

 Contractor Name:   King Solutions

Construction Start Date:  August 7, 2023

Substantial Completion Date:  December 11, 2023

Final Completion Date:  January 05, 2024

Project Overview: The contract is made up of 13 repair locations.

a. Pipe burst 3,453 LF of line 6" pipe, reconnect 65 sewer laterals, remove and replace 9 manholes, rehab 9 manholes and perform 6 point repairs. 

SEE PLANS HERE


 

Sanitary Sewer Bond Project

PHASE D

 Contractor Name:   T-Construction

Construction Start Date:  February 20, 2024

Substantial Completion Date:  July 28, 2024

Final Completion Date:  August 14, 2024

Project Overview:  The project bid package consists of a Base Bid and two Add Alternate Bids.

The Base Bid scope of work includes pipe bursting of 1878 LF of lined 6-inch to 8-inch pipe, replacing 63 LF of lined sewer pipe by open cut, reconnect 24 sewer laterals, remove, and replace manholes, rehabilitate 10 

manholes, install 1 cleanout, abandon 263 LF of lined 6” sanitary sewer pipe, three point repairs by open cut, and site restorations.

The Add Alternate 1 scope of work includes pipe bursting of 234 LF of lined 6-inch to 8-inch pipe, replacing 35 LF of lined sewer pipe by opencut, remove and replace 3 manhole structure, rehabilitate 1 manhole structure, reconnect 3 sewer laterals, and site restoration.

The Add Alternate 2 scope of work includes installing 415LF 6” PVC sanitary sewer pipe by open cut, installing5 cleanouts, installing 1 manhole, and site restoration.

SEE PLANS HERE

 

 

 

 

 

 

 
Olmos Park City Hall, 120 W El Prado Dr, Olmos Park, Texas 78212 Phone: 210-824-3281