PROJECT COMPLETED
Sanitary Sewer Bond Project
PHASE A
Contractor Name: Texas Pride Utilities
Construction Start Date: November 7, 2022
Substantial Completion Date: March 7, 2023
Final Completion Date: March 22, 2023
Project Overview: The project bid package consists of a Base Bid and three Add Alternate Bids.
Scope of work includes pipe bursting of 1878 LF of lined 6-inch to 8-inch pipe, replacing 63 LF of lined 6-inch sewer pipe by open cut, reconnect 24 sewer laterals, remove, and replace 9 manholes, rehabilitate 10 manholes, install 1 cleanout, abandon 263 LF of lined 6” sanitary sewer pipe, 3-point repairs by open cut, and site restorations.
SEE PLANS HERE
PROJECT COMPLETED
Sanitary Sewer Bond Project
PHASE B
Contractor Name: T-Construction
Construction Start Date: January 9, 2023
Substantial Completion Date: May 23, 2023
Final Completion Date: September 7, 2023
Project Overview: The project bid package consists of a Base Bid and three Add Alternate Bids. Work includes pipe bursting, reconnecting of sewer laterals, installing manholes and one terminal cleanout, performing point repairs, removing protruding tap using a robotic cutter, performing post-TV inspections, restoring landscape and doing appurtenant work.
SEE PLANS HERE
PROJECT COMPLETED
Street and Drainage Maintenance Project
Contractor Name: ONO Contracting, Inc.
Construction Start Date: TBD
Substantial Completion Date: TBD
Final Completion Date: TBD
Project Overview: The project bid package consists of milling, overlay and installing valley gutters on Park Hill Drive
PROJECT COMPLETED
Sanitary Sewer Bond Project
PHASE C
Contractor Name: King Solutions
Construction Start Date: August 7, 2023
Substantial Completion Date: December 11, 2023
Final Completion Date: January 05, 2024
Project Overview: The contract is made up of 13 repair locations.
a. Pipe burst 3,453 LF of line 6" pipe, reconnect 65 sewer laterals, remove and replace 9 manholes, rehab 9 manholes and perform 6 point repairs.
SEE PLANS HERE
Sanitary Sewer Bond Project
PHASE D
Contractor Name: T-Construction
Construction Start Date: February 20, 2024
Substantial Completion Date: July 28, 2024
Final Completion Date: August 14, 2024
Project Overview: The project bid package consists of a Base Bid and two Add Alternate Bids.
The Base Bid scope of work includes pipe bursting of 1878 LF of lined 6-inch to 8-inch pipe, replacing 63 LF of lined sewer pipe by open cut, reconnect 24 sewer laterals, remove, and replace 9 manholes, rehabilitate 10
manholes, install 1 cleanout, abandon 263 LF of lined 6” sanitary sewer pipe, three point repairs by open cut, and site restorations.
The Add Alternate 1 scope of work includes pipe bursting of 234 LF of lined 6-inch to 8-inch pipe, replacing 35 LF of lined sewer pipe by opencut, remove and replace 3 manhole structure, rehabilitate 1 manhole structure, reconnect 3 sewer laterals, and site restoration.
The Add Alternate 2 scope of work includes installing 415LF 6” PVC sanitary sewer pipe by open cut, installing5 cleanouts, installing 1 manhole, and site restoration.
SEE PLANS HERE